TX Pilot Time Offset Acceptance Test – continued
MAY 2004
7-17
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
Table 7-7: Test Pilot Time Offset
Step Action
5
Verify that the correct channel number for the selected carrier is shown in the Carrier # Channels
box.
– If it is not, obtain the latest bts–#.cdf and cbsc–#.cdf files from the CBSC.
NOTE
If necessary, the correct channel number may be manually entered into the Carrier # Channels box.
6 Click OK to display a status bar followed by a Directions pop-up window.
7 Follow the cable connection directions as they are displayed, and click the Continue button to begin
testing.
– As the ATP process is completed, results will be displayed in a status report window.
8 Click the Save Results or Dismiss button.
NOTE
If Dismiss is used, the test results will not be saved in the test report file.