User's Manual Part 2
Abbreviated (All–inclusive) Acceptance Tests – continued
MAY 2004
7-7
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
Table 7-2: All TX/RX ATP Test Procedure
Step Action
11 Click the Save Results or Dismiss button.
NOTE
If Dismiss is used, the test results will not be saved in the test report file.
All TX ATP Test
Follow the procedures in Table 7-3 to perform the abbreviated,
all–inclusive transmit test.
Table 7-3: All TX ATP Test Procedure
Step Action
1 Set up the test equipment for abbreviated tests per Table 7-1.
2 Select the BBXs and MCCs to be tested.
3 Click on Tests in the BTS menu bar, and select All TX ATP... from the pull–down menu.
4 Select the appropriate carrier(s) and sector(s) (carrier-bts#-sector#-carrier#) from those displayed in the
Channels/Carrier pick list.
NOTE
To select multiple items, hold down the Shift or Ctrl key while clicking on pick list items to select
multiple carrier(s)–sector(s).
5
Verify that the correct channel number for the selected carrier is shown in the Carrier # Channels
box.
– If it is not, obtain the latest bts–#.cdf and cbsc–#.cdf files from the CBSC.
NOTE
If necessary, the correct channel number may be manually entered into the Carrier # Channels box.
6 In the Test Pattern box, select the test pattern to use for the acceptance test from the drop–down list
(refer to “Test Pattern Drop–down Pick List” under “TX Calibration and the LMF” in the Bay Level
Offset Calibration section of Chapter 6.
7 Click OK to display a status bar followed by a Directions pop-up window.
8 Follow cable connection directions as they are displayed, and click the Continue button to begin
testing.
– As the ATP process is completed, results will be displayed in the status report window.
9 Click the Save Results or Dismiss button.
NOTE
If Dismiss is used, the test results will not be saved in the test report file.
All RX ATP Test
Follow the procedures in Table 7-4 to perform the abbreviated,
all–inclusive receive test.
7