User's Manual Part 1
Installation Completion Checklist – continued
MAY 2004
4-79
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
Table 4-42: Indoor Installation Completion Checklist
Status NotesItemNo.
36 Installation hardware is removed.
37 The earth ground connections are secure
between the earth ground and the Compact
BTS. (Indoor)
38 The DC input cable is securely attached to the
DC input connector. (Indoor)
39 The BTS–to–cCLPA cabling is secure (if
applicable) (Indoor)
40 cCLPA connection to earth ground is secure
(if cCLPA in use). (Indoor)
41 The antenna N–type connectors are securely
attached to the antenna A and B connectors
(if applicable). (Indoor)
42 All unused ports on BTS and/or cCLPA are
properly terminated. (Indoor)
43 All cables are dressed and tied. (Indoor)
44 Power, Span, Customer I/O, PA, RGPS, and
DO cables to the BTS have a ferrite core
attached and tie–wrapped in place.
45 The external power source (DC) is active.
(Indoor)
46 AC power source is active. (Outdoor)
47 The circuit breaker on the BTS is disengaged
(Pulled out).
48 Circuit breakers are disengaged (Pulled out)
on TME PDM. (Outdoor)
49 Circuit breakers are disengaged (Pulled out)
on PDE. (Outdoor)
50 Circuit breaker is disengaged (Pulled out) on
cCLPA.
51 The site is cleaned, swept and trash removed.
52 The site specific documentation is present at
the site.
4