Installation Completion Checklist
MAY 2004
4-77
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
Directions
Fill out the installation completion checklist and make any necessary
copies. You may copy this check sheet as needed.
Indoor Installation Completion
Checklist
Date Hardware Installation Completed: ________________________
Site:_______________________________________________________
Serial Number(s):__________________________
__________________________________________________________
Checklist Completed By:_____________________________________
Checklist Reviewed By:______________________________________
Table 4-42: Indoor Installation Completion Checklist
Status No. Item Notes
1 Equipment is not damaged.
2 Air flow clearance requirements are met.
3 Mounting plate is level and secure. (Indoor)
4 BTS is securely mounted to plate and rack.
(Indoor)
5 TME is securely mounted to wall or pole.
(Outdoor)
6 PDM is installed and cabled within TME.
(Outdoor)
7 BTS is securely mounted within the TME.
(Outdoor)
8 BTS is correctly cabled to TME.
9 1U Module is installed and cabled to TME (If
used).
10 HMS is securely mounted to TME. (Outdoor)
11 HMS is cabled to TME. (Outdoor)
12 PDE is securely mounted to wall or pole.
(outdoor)
13 HX is securely mounted to PDE. (Outdoor)
14 HX is cabled to PDE. (Outdoor)
15 TME, PDE, and cCLPA are grounded.
(Outdoor)
table continued next page
4