User's Manual Part 1
Thermal Management Enclosure Installation – continued
MAY 2004
4-23
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
TME Conduit Sizes
The following are the conduit sizes required for connecting to the TME.
Reference Figure 4-16.
Table 4-13: TME Conduit Sizes
No. Designation Required Size
(Inches)
1 Data and Expansion 1–1/2
2 TME Power Input 1
3 Fiber Optic 1/2
Materials
Tools
The following tools are required to install the TME:
S Torque Screwdriver
S Drill, 3/8–inch or 1/2–inch drive
S Appropriate concrete or wood drill Bits
S Tie–Wraps
S Appropriate size conduit (Metallic sealtight)
S Bucklestrap Cutting Tool (Motorola P/N 6604809N01)
S Safety Glasses
S Heavy Gloves
S Electrical Tape
S Tape Measure
S Hammer, ball–peen
TME Installation
Pole Mount
Follow the procedure in Table 4-14 to pole mount the TME. Figure 4-17
shows the Mounting Bracket Assembly and Wall Mounting Bracket.
Check site documents to verify that pole and supporting hardware are
capable of handling the load created by mounting the BTS system.
Once TME is installed, DO NOT use it as a step ladder. It
will not support a person standing on top or hanging from
it.
WARNING
4