User's Manual Part 1
Installation Overview
MAY 2004
4-1
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
Overview
This chapter provides the procedures for BTS installation and cabling.
The site cabling has been installed and routed to the location of the BTS.
In this chapter, the cables will be attached to the unit(s). Cabling
installation will be repeated as necessary for each unit at the BTS.
This chapter provides the information and procedures to:
S Assembling the BTS mounting hardware
S Attach cables to the BTS
S Power to BTS
S Complete the installation completion checklist
Procedure order
Indoor
The process of installing the indoor unit requires that the following
procedures be completed in the order shown:
1. Mount and secure Mounting Plate to rack
2. Attach angle bracket to BTS
3. Secure BTS to the Mounting Plate
4. Attach Earth ground cable to BTS
5. Connect DC Power cable to BTS
6. Attach antenna cable
7. Mount and secure cCLPA mounting bracket to rack (if used)
8. Mount and secure cCLPA to mounting bracket (if used).
9. Attach Earth ground cable to cCLPA
10. Connect DC Power cable to cCLPA
11. Connect data cable between cCLPA and BTS
12. Terminate unused connectors
13. Perform Pre–Power checks
14. Power on the units
15. Clean up site
16. Fill out the installation completion checklist
Outdoor
The process of installing the outdoor unit requires that the following
procedures be completed in the order shown:
1. Attach the mounting brackets to wall or pole mounting bracket
assemblies
2. Detach HMS from TME
3. Mount TME onto mounting bracket
4