User's Manual

Table Of Contents
RFDS Set–up and Calibration
68P64115A18–1
Mar 2003
1X SC 4812T Lite BTS Optimization/ATP Software Release R2.16.1.x
DRAFT
3-108
Program TSU NAM
The NAM must be programmed before it can receive and process test
calls, or be used for any type of RFDS test.
Prerequisites
S MGLI is INS_ACT (bright green).
S SUA is powered up and has a code load.
Follow the procedure in Table 3-46 to program the TSU NAM.
Table 3-46: Program NAM Procedure
Step Action
1 In the LMF, select the RFDS tab.
2 Select the SUA by clicking on it.
3 Click on TSU in the BTS menu bar, and select Program TSU NAM from the pull–down menu.
A NAM programming window will appear.
4 Enter the appropriate information in the boxes (see Table 3-40 and Table 3-41) .
5 Click on the OK button to display the status report.
6 Click on the OK button to close the status report window.