BTS 120 Degree Sector (3 Sector) Receive Path Cabling
68P64115A194
Mar 2003
1X SC 4812T-MC BTS Hardware Installation - Software Release R2.16.1.x
CONTROLLED INTRODUCTION
2-39
Cabling Procedure
Install each cable by referring to the cable run list in Table 2-30, the
cabling diagram in Figure 2-17, and the procedure in Table 2-31. Each
cable is installed the same way.
Table 2-31: Installing the 120 Degree Sector Receive Path Cables
Step Action
1 Attach the connector-equipped end of the cables to the BTS RX connectors.
2 Route the cables to the lightning arrestors.
3 Cut the cables to length and label them accordingly. Install connectors on the cables, and attach the
cables to the lightning arrestors.