User's Manual
Table Of Contents
- SC 4812T-MC vs SC 4812T BTS Read Me First (Comparison)
- Contents
- Chapter 1 Manual Overview and BTS General Information
- Chapter 2 Inter-Frame Cabling
- Inter-Frame Cabling
- Cable Connections
- Cabling Diagrams and Descriptions
- Alarm / Span Cabling
- Equipment Compliance
- BTS System Timing Options
- RF Global Positioning Satellite (RF GPS) Cabling
- Remote Global Positioning Satellite (RGPS) Cabling
- Low Frequency Receiver / High Stability Oscillator (LFR/HSO) Cabling
- BTS Antenna Configuration
- BTS 60 Degree Sector (6 Sector) Transmit Path Cabling
- BTS 60 Degree Sector (6 Sector) Receive Path Cabling
- BTS 120 Degree Sector (3 Sector) Transmit Path Cabling
- BTS 120 Degree Sector (3 Sector) Receive Path Cabling
- Earth Ground Cabling
- BTS Power Cabling
- Chapter 3 Expansion Frame Cabling and Installation
- Expansion Frame (+27 V BTS Configuration)
- Expansion Frame Inter-Frame Cabling
- Expansion of the +27 V Frame
- RF GPS Expansion Installation
- Remote GPS Distribution Expansion
- High Stability Oscillator Expansion (HSOX)
- Local Area Network (LAN) Expansion Installation
- Setting Frame C-CCP Shelf Configuration Switch
- Chapter 4 Optional Equipment
- Optional BTS Equipment Identification
- BTS Antenna Configuration
- BTS 60 Degree Sector (6 Sector) Transmit Path Cabling
- BTS 60 Degree Sector (6 Sector) Receive Path Cabling
- BTS 120 Degree Sector (3 Sector) Transmit Path Cabling
- BTS 120 Degree Sector (3 Sector) Receive Path Cabling
- 3 Sector Non-Duplexed Cabling
- 3 Sector Duplexed
- 6 Sector Duplexed
- Chapter 5 What's Next and Site Cleanup
- Appendix A Carrier Add Instructions
- Index
Installation Completion Checklist
68P64115A19–4
Mar 2003
1X SC 4812T-MC BTS Hardware Installation - Software Release R2.16.1.x
CONTROLLED INTRODUCTION
5-4
Installation Completion Checklist
Directions
Fill out the installation completion checklist and make any necessary
copies. You may copy this check sheet as needed.
Installation Completion Checklist
Date Hardware Installation Completed:
Site:
Master BTS Frame Serial Number:
Expansion BTS Frame Serial Number(s):
Checklist Completed By:
Checklist Reviewed By:
Table 5-1: Installation Completion Checklist
Status No. Item Notes
1 Frames are bolted down.
2 DC power cabling completed.
3 Each frame has its own earth ground.
4 RX RF cables installed.
5 TX RF cables installed.
6 LAN cables installed.
7 Span line cables installed.
8 Alarm cables installed.
9 Modem cables installed.
10 GPS antenna installed.
11 LFR antenna installed (if required).
12 GPS antenna cabling installed.
13 LFR antenna cabling installed (if required).
14 RF connectors are tight.
15 Power connections are tight.
16 RF cables are labeled the same at both ends.
17 Data cables labeled at both ends.
18 Remote GPS (if required).
19 Remote GPS cables (if required).
20 Ethernet LAN cables and terminators
installed.
. . . continued on next page