User's Manual
Table Of Contents
- SC 4812T-MC vs SC 4812T BTS Read Me First (Comparison)
- Contents
- Chapter 1 Manual Overview and BTS General Information
- Chapter 2 Inter-Frame Cabling
- Inter-Frame Cabling
- Cable Connections
- Cabling Diagrams and Descriptions
- Alarm / Span Cabling
- Equipment Compliance
- BTS System Timing Options
- RF Global Positioning Satellite (RF GPS) Cabling
- Remote Global Positioning Satellite (RGPS) Cabling
- Low Frequency Receiver / High Stability Oscillator (LFR/HSO) Cabling
- BTS Antenna Configuration
- BTS 60 Degree Sector (6 Sector) Transmit Path Cabling
- BTS 60 Degree Sector (6 Sector) Receive Path Cabling
- BTS 120 Degree Sector (3 Sector) Transmit Path Cabling
- BTS 120 Degree Sector (3 Sector) Receive Path Cabling
- Earth Ground Cabling
- BTS Power Cabling
- Chapter 3 Expansion Frame Cabling and Installation
- Expansion Frame (+27 V BTS Configuration)
- Expansion Frame Inter-Frame Cabling
- Expansion of the +27 V Frame
- RF GPS Expansion Installation
- Remote GPS Distribution Expansion
- High Stability Oscillator Expansion (HSOX)
- Local Area Network (LAN) Expansion Installation
- Setting Frame C-CCP Shelf Configuration Switch
- Chapter 4 Optional Equipment
- Optional BTS Equipment Identification
- BTS Antenna Configuration
- BTS 60 Degree Sector (6 Sector) Transmit Path Cabling
- BTS 60 Degree Sector (6 Sector) Receive Path Cabling
- BTS 120 Degree Sector (3 Sector) Transmit Path Cabling
- BTS 120 Degree Sector (3 Sector) Receive Path Cabling
- 3 Sector Non-Duplexed Cabling
- 3 Sector Duplexed
- 6 Sector Duplexed
- Chapter 5 What's Next and Site Cleanup
- Appendix A Carrier Add Instructions
- Index
Site Cleanup
68P64115A19–4
Mar 2003
1X SC 4812T-MC BTS Hardware Installation - Software Release R2.16.1.x
CONTROLLED INTRODUCTION
5-3
Site Cleanup
Remove Protective Covering
Remove any cardboard from the walls used to protect the walls.
Remove any antistatic plastic or cloth sheeting used to cover the
equipment.
Lighting Fixtures
Remove any masking tape from the fluorescent light fixtures.
Tools
Place all hand and power tools in the installation tool kit or other
appropriate place. Note any tools needing replacement, cleaning, or
adjustment.
Materials
Place any leftover materials in a location specified by the site manager.
Remove Debris
Remove any packing material.
Ensure that all scrap materials have been removed from any tables or
stands.
Clean/sweep the floor. Ensure all chalk line marks have been removed.
Environment
Check that all covers, frame doors, and fan housings are in place.
Confirm all power connections are tight.
Organize any items (manuals, materials, etc.) left on site and place them
in a safe location specified by the site manager.
5