User's Manual

Table Of Contents
BTS 120 Degree Sector (3 Sector) Receive Path Cabling
68P64115A194
Mar 2003
1X SC 4812T-MC BTS Hardware Installation - Software Release R2.16.1.x
CONTROLLED INTRODUCTION
4-16
Cabling Procedure
Install each cable by referring to the cable run list in Table 4-11, the
cabling diagram in Figure 4-8, and the procedure in Table 4-12. Each
cable is installed the same way.
Table 4-12: Installing the 120 Degree Sector Receive Path Cables
Step Action
1 Attach the connector-equipped end of the cables to the BTS RX connectors.
2 Use the following step to connect the DDCs to the antenna system.
Cut the cables to length and label them accordingly. Install connectors on the cables and attach
the cables to the DDCs RX connector or BTS connectors.
Attach the connector-equipped end of additional cables to the DDCs’ ANT connectors.
3 Route the cables to the lightning arrestors.
4