BTS 60 Degree Sector (6 Sector) Transmit Path Cabling
68P64115A19–4
Mar 2003
1X SC 4812T-MC BTS Hardware Installation - Software Release R2.16.1.x
CONTROLLED INTRODUCTION
4-9
60 Degree Sector Configuration
Table 4-2 provides the Cable Run List for 60 degree sector transmit
paths.
Table 4-2: Cable Run List for 60 Degree Sector TX Configuration
Cable Cable Parts Connecting Lightning Arrestors To BTS TX Connectors
G via Directional Coupler via DDC BTS TX Ports
Quantity 12 18 TX1 to TX6
Procedure
Install each cable by using the cable run list in Table 4-2, the cabling
diagram in Figure 4-5, and the procedure in Table 4-3. Each cable is
installed the same way.
Table 4-3: Installing the 60 Degree Sector TX Path Cables
Step Action
1 Attach the connector–equipped end of the cables to the BTS TX connectors.
2 Route the cables to the DCs or DDCs.
3 Cut the cables to length and label them accordingly. Install connectors on the cables and attach the
cables to the DDCs TX connector or Directional Couplers BTS connectors.
4 Attach the connector-equipped end of additional cables to the DDCs or Directional Couplers ANT
connectors.
5 Route the cables to the lightning arrestors.