Site Checklist
Table A-2: Site Checklist
OK Parameter Specification Comments
− Deliveries Per established procedures
− Floor Plan Verified
−
−
−
Inter Frame Cables:
Ethernet
Frame Ground
Power
Per procedure
Per procedure
Per procedure
−
−
−
Factory Data:
BBX
Test Panel
RFDS
Per procedure
Per procedure
Per procedure
− Site Temperature
− Dress Covers/Brackets
Preliminary Operations
Table A-3: Preliminary Operations
OK Parameter Specification Comments
− Frame ID DIP Switches Per site equipage
− Ethernet LAN verification Verified per procedure
Comments:_________________________________________________________