User Manual

Automated Acceptance Test Procedure Overview continued
SC4812ET BTS Optimization/ATP CDMA LMF
Jan 2002
4-4
ATP Test Procedure
There are three different ATP testing options that can be performed to
completely test a BTS. Depending on your requirements, one of the
following ATP testing options should be run. Table 4-1 provides the
procedure to execute an ATP test. To completely test a BTS, run the ATP
tests according to one of the following ATP testing options.
ATP Testing Option 1
All TX/RX test
ATP Testing Option 2
All TX test
All RX test
ATP Testing Option 3
TX Mask test
Rho test
Pilot Time Offset test
Code Domain Power test
FER test
The Full Optimization test can be run if you want the TX
path calibrated before all the TX and RX tests are run.
NOTE
If manual testing has been performed with the HP analyzer,
remove the manual control/system memory card from the
card slot and set the IO CONFIG to the Talk & Listen
mode before starting the automated testing.
IMPORTANT
*
CDMA 2000 Testing
Software release 2.16.x supports two new pieces of test equipment.
These are the Agilent E4406A with E4432B, as well as the Advantest
R3267 with R3562. The E4406A/E4432B pair, or the R3267/R3562
pair, should be connected together using a GPIB cable. This test
equipment is capable of performing tests in both IS95 mode as well as
cdma2000 mode if the required options are installed:
The HP 8935 with option 200 or R2k for 1X TX and with Agilent
E4432B Signal Generator for 1X FER
4