User's Manual

Initial Power-up
68P09255A69-3
Aug 2002
1X SC4812ET Lite BTS Optimization/ATP Software Release 2.16.1.x
PRELIMINARY
2-8
Figure 2-6: DC PDA
SC4812ETL0009-3
LPA
1B 1D 3B 3D
1A 1C 3A 3C PS1 PS2
ETIB
OPTIONS
25 25
HEAT EXCHANGER
CAUTION
SHUT OFF BOTH BREAKERS
ONLY DURING HEAT EXCHANGER
MAINTENANCE OR REPAIR
LPA
BLOWERS
PUSH BUTTON
TO RESET
LPA BLOWERS
MAIN BREAKER
300
50 5010 1530 30 30 30 15
PILOT
BEACON
DC Power System Pre-power Application Test
Before applying any power to the BTS frame, follow the procedure in
Table 2-3 to verify there are no shorts in the DC power distribution
system.
NOTE
The procedure in Table 2-3 is required only on initial frame
power-up or following maintenance when any major power
components (e.g., ACLC, DC PDA, Meter Alarm Panel) were
replaced or internal DC power cables were disconnected.
Table 2-3: DC Power System Pre-Power Application Test
Step Action
1 Physically verify all ACLC front-panel circuit breakers (Figure 2-4) are OFF (down), all DC PDA
circuit breakers (Figure 2-6) are set to OFF (pulled out), and all battery shelf circuit breakers
(Figure 2-3) are OFF (pulled out).
2 Visually ensure that all AC rectifier modules (Figure 2-3) are not powered (DC, PWR, and bar graph
LEDs are not lighted), that the MAP power switch (Figure 2-9) is OFF, and that no LEDs on the
MAP are lighted.
3 Inside the battery compartment, measure the voltage between the + (red) and - (black) battery bus
bars. There should be no 27 Vdc present.
4
NOTE
Do not unseat the AC rectifier modules in the following step.
Perform the following:
4a - In the frame RF compartment, unseat all circuit boards/ modules (except CCD and CIO cards) in
the SCCP shelf, but leave them in their respective slots.
4b - In the frame LPA compartment, disconnect the Linear Power Amplifier (LPA) cables from the
compartment bulkhead feed-through connector.
5 Set the DMM to measure resistance, and inside the battery compartment, measure the resistance
between the + (red) and - (black) battery bus bars. The resistance should measure >
1 ΜΩ.
6 Leave the DMM set to measure resistance, and insert the probes into the MAP VOLT and AMP TEST
POINTS (Figure 2-9). Place the (+) DMM probe into the (-) AMP TEST POINT. Place the (-) DMM
probe into the (-) VOLT TEST POINT. Resistance should measure greater than 750 .
. . . continued on next page
2