User's Manual
Optimization (Pre-ATP) Data Sheets68P09255A69-3
Aug 2002
1X SC4812ET Lite BTS Optimization/ATP Software Release 2.16.1.x
PRELIMINARY
A-3
Site Checklist
Table A-2: Site Checklist
OK Parameter Specification Comments
Deliveries Per established procedures
Floor Plan Verified
Inter Frame Cables:
Ethernet
Frame Ground
Power
Per procedure
Per procedure
Per procedure
Factory Data:
BBX
Test Panel
RFDS
Per procedure
Per procedure
Per procedure
Site Temperature
Dress Covers/Brackets
Preliminary Operations
Table A-3: Preliminary Operations
OK Parameter Specification Comments
Frame ID DIP Switches Per site equipage
Ethernet LAN verification Verified per procedure
Comments:_________________________________________________________
A