User's Manual
Prepare to Leave the Site
68P09255A69-3
Aug 2002
1X SC4812ET Lite BTS Optimization/ATP Software Release 2.16.1.x
PRELIMINARY
5-6
Table 5-6: Remove LMF
Step Action
5 Disconnect the LMF terminal Ethernet port from the BTS frame.
6 Disconnect the LMF terminal serial port, the RS-232-to-GPIB interface box, and the GPIB
cables as required for equipment transport.
Connecting BTS T1/E1 Spans
Before leaving the site, connect any T1 or E1 span connectors removed
previously to allow the LMF to control the BTS. Refer to Table 5-7 and
Figure 3-2.
Table 5-7: Connect T1 or E1 Spans
Step Action
1 Re-connect any disconnected span connectors to the Span I/O A and B boards.
2 If equipped, ensure the CSU is powered on.
3 Verify span status, ensuring the OMC-R/CBSC can communicate with the BTS.
Before Leaving the site
Be sure all requirements listed in Table 5-8 are completed before leaving
the site.
Table 5-8: Check Before Leaving the Site
Step Action
1 When backup batteries are installed, all battery circuit breakers are ON (pushed in).
2 Both heat exchanger circuit breakers on the DC PDA are set to ON (pushed in), and the heat
exchanger blowers are running.
3 The External Blower Assembly (EBA) power cable is connected, and the EBA is running.
4 The MAP power switch is set to ON, and the POWER (green) LED is lighted.
5 The MAP TCP switch is set to ON.
6 The BATT TEST switch on the MAP is set to OFF, and the BATT. TEST (amber) LED is not lighted.
7 No alarm conditions are being reported to the CBSC with all frame doors closed.
5