User's Manual

Table Of Contents
Initial Power-up Tests
68P09255A61-4
Aug 2002
1X SC 4812T BTS Optimization/ATP Software Release 2.16.1.x
FIELD TRIAL
2-16
Table 2-7: Initial Power-up (BTS)
Step Action
7 Set the LPA breakers to the ON position (per configuration) by pushing them IN one at a time. See
Figure 1-13 on page 1-33 or Figure 1-14 on page 1-34 for configurations and Figure 2-3 on page 2-8
or Figure 2-5 on page 2-10 for LPA breaker panel layout.
On +27 V frames, engage (push) LPA circuit breakers.
Confirm LEDs on LPAs light.
On -48 V frames, engage (push) LPA PS circuit breakers.
Confirm LPA PS fans start.
Confirm LEDs on -48 V power converter boards light.
Confirm LPA fans start.
Confirm LEDs on LPAs light.
8 After all cards/modules have been seated and verified, use a digital voltmeter to verify power supply
output voltages at the top of the frame remain within specifications: +27.0 Vdc or -48 Vdc
nominal.
9 Repeat Steps 1 through 8 for additional co-located frames (if equipped).
2