User's Manual

Table Of Contents
Automated Acceptance Test Procedures - All-inclusive TX & RX68P09255A61-4
Aug 2002
1X SC 4812T BTS Optimization/ATP Software Release 2.16.1.x
FIELD TRIAL
4-3
Reduced ATP
NOTE
Equipment has been factory-tested for FCC compliance. If
license-governing bodies require documentation supporting
SITE compliance with regulations, a full ATP may be necessary.
Perform the Reduced ATP only if reports for the specific BTS
site are NOT required.
After downloading the proper operational software to the BTS, the CFE
must perform these procedures (minimal recommendation):
1. Verify the TX/RX paths by performing TX Calibration, TX Audit
and FER tests.
2. Retrieve Calibration Data required for normal site operation.
Should failures occur while performing the specified tests, refer to the
Basic Troubleshooting section of this manual for help in determining the
failure point. Once the point of failure has been identified and corrected,
refer to the BTS Optimization and ATP Test Matrix section
(Appendix C) to determine the applicable test that must be performed.
In the unlikely event that the BTS passes these tests but has a forward
link problem during normal operation, the CFE should then perform the
additional TX tests for troubleshooting: TX spectral mask, TX rho, and
TX code domain.
Required Test Equipment
The following test equipment is required:
LMF
Power meter (used with HP8921A/600 and Advantest R3465)
Communications system analyzer
Signal generator for FER testing (required for all communications
system analyzers for 1X FER)
WARNING
- Before installing any test equipment directly to any BTS
TX OUT connector, verify that there are no CDMA
channels keyed.
- At active sites, have the OMCR/CBSC place the carrier
assigned to the LPAs under test OOS. Failure to do so can
result in serious personal injury and/or equipment damage.
NOTE
The test equipment must be re-calibrated before using it to
perform the TX Acceptance Tests.
4