Objective
The objective of this procedure is to attach the AC input power cable to
the unit. Use this procedure only when AC power is used to power the
unit.
If the Primary Surge Suppressor is not used, the AC Installation Box is
required for all outdoor mounting applications.
This equipment uses dangerous voltages and is capable of
causing death. Use extreme caution when handling and
testing this equipment.
WARNING
Required Cables
The following cables in Table 4-1 are necessary to do this procedure:
Table 6-16: Required Cables for AC Input Power Cabling
Cable Qty. Part Number Description
S 1–4 3087854C02 AC input cable, 18 AWG, 5 m, is designed for 120–240 VAC power
input. Cable has Deutsche connector on both ends.
Power Cable and Connector
Signal Information
The AC input connector is located on the side of the unit as shown in
Figure 6-15. The unit is designed for 88–260 VAC power input.
Procedure to Connect AC Input
Power Cable to the Unit
Use the following procedure in Table 6-17 to connect the AC input cable
to the unit. The AC input cable should be connected before the solar
cover is attached.
Table 6-17: Procedure to Connect AC Power Cable to the Unit
Step Action
1 Ensure that the ground wire has a connection to the Master Ground Bus (also called Master
Ground Plate).
2 Verify that the AC power breaker is open. The white collar on the breaker is visible when it is
open.
3 Place the round, black connector on the AC input cable (cable S) onto the AC input connector.
See Figure 6-15. Turn the cable connector to align its key.
4 Hand tighten the connector (a clicking sound is heard, this is normal). When the red line on the
connector on the unit is covered, connection is complete.