Objective
The objective of this procedure is to install span line cabling between
multiple BTS sites equipped with Primary Surge Suppressor in an open
daisy chain configuration.
Background
This feature allows multiple BTS sites to be linked together in an open
daisy chain loop using a single T1/E1 span. This will reduce the number
of spans necessary to support a CDMA system and minimize unused
channels.
Each BTS site may contain up to four units. A maximum of 12 BTS
sites may be combined in a single daisy chain.
Required Cables
The following cables are necessary to do this procedure.
Table 5-24: Required Cables for Span Line Daisy Chain Cabling
Cable Qty. Part Number Description
W 13 Customer
Supplied
Span Line Daisy Chain Cable
Procedure
Attach the span line daisy chain cable (Cable W) to the site I/O interface
of each BTS site. Refer to Figure 5-23 and Table 5-25.
Cable Connections
Table 5-25 shows the cable run information for span line daisy chain
cabling for BTS sites equipped with the Primary Surge Suppressor.
For a full signal description of the Site I/O cable refer to Table 5-14 in
the Site I/O, Span Line, RGPS and Modem Cabling for Sites Equipped
with Optional Primary Surge Suppressor procedure.
The pin number and wire color are based on the Site I/O
cable. The pin number corresponds to pins on the Site I/O
junction box connectors.
NOTE
5