User's Manual

Power, Ground, and Battery Cabling for Sites Equipped with
CustomerSupplied Site I/O Interface
continued
DRAFT
SC300 1X BTS Hardware Installation, ATP, and FRU Procedures
JAN 2002
4-14
Figure 4-7: AC Installation Box
AC POWER CABLE
CONNECTOR
NOTE: Shown with door removed for clarity
1IN AC
CONDUIT
TO MICROCELL
LOCATION
CUSTOMER
AC INPUT
TERMINAL
BLOCK
LINE
NEUTRAL
GROUND
CUSTOMER POWER
CONNECTIONS
Table 4-19: Procedure to Install DC Input Cable(s)
Step Action
1 Connect the loose wires of cable U (DC input cable) to the customer defined DC power source.
Refer to Table 4-14 for wiring information.
2 Verify all connections of cable U with an multimeter prior to routing the cable.
3 Route cable U from the DC power supply to the unit location.