Power, Ground, and Battery Cabling for Sites Equipped with
Customer–Supplied Site I/O Interface
– continued
JAN 2002
4-13
SC300 1X BTS Hardware Installation, ATP, and FRU Procedures
DRAFT
Table 4-15: Procedure to Install Earth Ground Cable
Step Action
1 Route cable Y (ground cable) from the ground on the mounting bracket to the customer defined
grounding location.
2 Connect cable Y to the customer defined master ground plate.
Table 4-16: Procedure to Install AC Input Cable(s) (Indoor Applications)
Step Action
1 If you will not use the AC Installation box, cut off the male connector (with pins) from the AC
input power cable (cable S).
2 Connect the loose wires of cable S (AC input cable) to the customer defined AC power source.
Refer to Table 4-13 for wiring information.
3 Verify all connections of cable S with an ohmmeter prior to routing the cable.
4 Route cable S from the AC power supply to the unit location.
Table 4-17: Procedure to Install AC Installation Box (Optional – Required for Outdoor Installations)
Step Action
1 Route the AC Power Cable (cable T) through 1–in. conduit from the customer–defined AC power
source to the AC Installation box. Refer to Figure 4-7 and Table 4-18.
2 Attach the wires of cable T to the AC Installation Box terminal block. Refer to Figure 4-7 and
Table 4-18.
3 Place the round, black connector on the AC input cable (cable S) onto the AC power cable
connector on the AC installation box. Turn the cable connector to align its key.
4 Route cable S from the AC installation box to the unit location.
Table 4-18: AC Installation Box Cabling
Punchdown Block
Connector
AC Power Cable
Wire Color
Description
L Black Line
N White Neutral
GROUND Green Ground
4