User's Manual

BTS Preparation
DRAFT
SC300 1X BTS Hardware Installation, ATP, and FRU Procedures
JAN 2002
7-2
Overview
The purpose of this procedure is to prepare the BTS for the ATP. This
procedure consists of:
1. Solar Cover Removal
2. BTS Power Up
3. Diagnostic Access Cover Removal
Required Tools and Equipment
The following tools and materials are necessary to do this procedure:
Torque driver wrench, 1/4in. hex female drive, 010 NM
T20 Torx tamper bit
Procedure to Remove the Solar
Cover
If you did not mount the solar cover during the unit installation, then this
procedure is not necessary.
Remove the four captive screws (two on each side) that hold the front
solar cover. Refer to Figure 7-1.
Figure 7-1: Front Solar Cover
FRONT COVER
CAPTIVE SCREWS
CAPTIVE SCREWS
BTS Power Up
Figure 7-2 shows the location of the AC power breakers inside the
optional Primary Surge Suppressor. The AC breakers must be closed
before you power up the MicroCell unit.
Figure 7-3 shows the location of the AC and DC Power breakers on the
unit. Push both the AC and DC breakers in to power up the unit.
7