User's Manual

Connect Test Equipment to BTS
DRAFT
SC300 1X BTS Hardware Installation, ATP, and FRU Procedures
JAN 2002
7-10
Overview
The following test equipment setup applies to the BTS Acceptance Test
Procedure (ATP).
The SC300 BTS supports the following test sets for IS95 A/B testing:
1. Advantest R3465 with R3561 Signal Generator.
2. Motorola CyberTest
3. HP 8921A (for 800 MHz testing only)
4. Aglient 8935 Series E6380A (formally HP8935)
The 1X SC300 BTS supports the following test sets for CDMA2000
1X testing:
1. Advantest R3267 with R3562 Signal Generator
2. Agilent E4406A with E4432B Signal Generator
If you are not going to perform the ATP, then proceed to
the Creating a Named HyperTerminal Connection for
MMI Communication procedure in this chapter.
NOTE
Equipment warm-up
Warm-up BTS equipment site for a minimum of 60
minutes prior to the BTS ATP. This assures BTS site
stability and contributes to test accuracy.
(Time spent running initial powerup, hardware/firmware
audit, and BTS download counts as warmup time).
IMPORTANT
*
Warm-up test equipment for a minimum of 60 minutes
prior to their use in the BTS ATP. This assures maximum
equipment measurement accuracy and consistency during
testing.
IMPORTANT
*
All test equipment is controlled by the LMF via a Serial Cable/GPIB
bus. The LMF expects each piece of test equipment to have a factory-set
GPIB address. If there is a communications problem between the LMF
and any piece of test equipment, you should verify that the GPIB
addresses have been set correctly.