User's Manual Part 3

Appendix A: Optimization (PreATP) Data Sheets continued
Apr 2001
A-3
SC4812ET BTS Optimization/ATP CDMA LMF
DRAFT
PrePower and Initial Power
Tests
Table A3a: Prepower Checklist
OK Parameter Specification Comments
Prepowerup tests Verify power supply
output voltage at the top
of each BTS frame is
within specifications
Internal Cables:
ISB (all cages)
CSM (all cages)
Power (all cages)
Ethernet Connectors
LAN A ohms
LAN B ohms
LAN A shield
LAN B shield
Ethernet Boots
verified
verified
verified
verified
verified
isolated
isolated
installed
Air Impedance Cage (single cage) installed
Initial powerup tests Verify power supply
output voltage at the top
of each BTS frame is
within specifications:
Comments:_________________________________________________________
A