CSM System Time GPS & LFR/HSO Verification continued
DRAFT
SC4812ET BTS Optimization/ATP CDMA LMF
Apr 2001
3-34
CSM Frequency Verification
The objective of this procedure is the initial verification of the CSM
boards before performing the rf path verification tests. Parts of this
procedure will be repeated for final verification after the overall
optimization has been completed.
Test Equipment Setup
(GPS & LFR/HSO Verification)
Follow the steps outlined in Table 3-18 to set up test equipment.
Table 3-18: Test Equipment Setup (GPS & LFR/HSO Verification)
Step Action
1a For local GPS (RFGPS): Verify a CSM board with a GPS receiver is installed in primary CSM slot 1
and that CSM1 is INS.
NOTE
This is verified by checking the board ejectors for kit number SGLN1145 on the board in slot 1.
1b For Remote GPS (RGPS):Verify a CSM2 board is installed in primary slot 1 and that CSM1 is INS.
NOTE
This is verified by checking the board ejectors for kit number SGLN4132CC (or subsequent).
2 Remove CSM2 (if installed) and connect a serial cable from the LMF COM 1 port (via null modem
board) to the MMI port on CSM1 (see Figure 3-7).
3 Reinstall CSM–2.
4 Start an MMI communication session with CSM1 by using the Windows desktop shortcut icon (see
Table 3-5)
NOTE
The LMF program must be running when a Hyperterminal session is started.
5 When the terminal screen appears press the Enter key until the CSM> prompt appears.
Connect GPS antenna to the (GPS) RF connector
ONLY. Damage to the GPS antenna and/or receiver
can result if the GPS antenna is inadvertently connected
to any other RF connector.
CAUTION
3