User's Manual Part 1
Optimization Overview
Apr 2001
1-1
SC4812ET BTS Optimization/ATP — CDMA LMF
DRAFT
Scope of This Document
This document provides information pertaining to the optimization and
audit tests of Motorola SC 4812ET Base Transceiver Subsystem (BTS)
equipment frames equipped with trunked high–power Linear Power
Amplifiers (LPAs) and their associated internal and external interfaces.
This document assumes the following prerequisites: The BTS frames
and cabling have been installed per the
BTS Hardware Installation Manual
– 68P64114A22, which covers the physical “bolt down” of all SC series
equipment frames, and the specific cabling configurations.
Document Composition
This document covers the following major areas:
Introduction, consisting of preliminary background information (such
as component and subassembly locations and frame layouts) to be
considered by the Cell Site Field Engineer (CFE) before optimization
or tests are performed.
Preliminary Operations, consisting of cabinet power up and power
down procedures.
Optimization/calibration, covering topics of Local Maintenance
Facility (LMF) connection to the BTS equipment, Global Positioning
System (GPS) Verification, test equipment setup, downloading all
BTS processor boards, RF path verification, Bay Level Offset (BLO)
calibration and calibration audit, and Radio Frequency Diagnostic
System (RFDS) calibration.
Acceptance Test Procedures (ATPs), consisting of ATP tests executed
by the LMF and used to verify all major transmit (TX) and
receive (RX) performance characteristics on all BTS equipment.
Preparing to leave the site, presents instructions on how to properly
exit customer site, ensure that all equipment is operating properly, and
all work is complete according to Motorola guidelines.
Basic troubleshooting, consisting of procedures for installation,
calibration, transmit and receive tests, backplane problems, GPS
failures, and module connectors.
Appendices contain pertinent Pseudorandom Noise (PN) Offset,
frequency programming, output power data tables, data sheets that are
filled out manually by the CFE at the site, and information on test
equipment preparation.
1