Manual

Optimization (Pre–ATP) Data Sheets68P09258A31–A
Oct 2003
1X SCt 4812T BTS Optimization/ATP
A-3
Site Checklist
Table A-2: Site Checklist
OK Parameter Specification Comments
Deliveries Per established procedures
Floor Plan Verified
Inter Frame Cables:
Ethernet
Frame Ground
Power
Per procedure
Per procedure
Per procedure
Factory Data:
BBX
Test Panel
RFDS
Per procedure
Per procedure
Per procedure
Site Temperature
Dress Covers/Brackets
Preliminary Operations
Table A-3: Preliminary Operations
OK Parameter Specification Comments
Shelf ID Dip Switches Per site equipage
BBX Jumpers Verified per procedure
Ethernet LAN verification Verified per procedure
Comments:_________________________________________________________
A