User's Manual

Optimization/Calibration – Introduction
May 2000
3-1
SC 4812T CDMA BTS Optimization/ATP
Introduction
This section describes procedures for downloading system operating
software, CSM reference verification/optimization, set up and calibration
of the supported test equipment, transmit/receive path verification, and
using the RFDS.
Before using the LMF, use an editor to view the
”CAVEATS” section in the ”readme.txt” file in the c:\wlmf
folder for any applicable information.
IMPORTANT
*
Optimization Process
After a BTS is physically installed and the preliminary operations
(power up) have been completed, the LMF is used to calibrate and
optimize the BTS. Motorola recommends that the optimization be
accomplished as follows:
1. Download MGLI2–1 with code and data and then enable MGLI2–1.
2. Use the status function and verify that all of the installed devices of
the following types respond with status information: CSM, BBX2,
GLI2, and MCC (and TSU if RFDS is installed). If a device is
installed and powered up but is not responding and is colored gray in
the BTS display, the device is not listed in the CDF file. The CDF
file will have to be corrected before the device can be accessed by
the LMF.
3. Download code and data to all devices of the following types:
CSM
BBX2
GLI2 (other than MGLI2–1)
MCC
4. Download the RFDS TSIC (if installed).
5. Verify the operation of the GPS and HSO signals.
6. Enable the following devices (in the order listed):
Secondary CSM
Primary CSM
All MCCs
7. Connect the required test equipment for a full optimization.
8. Select the test equipment.
9. Calibrate the TX and RX test cables if they have not previously been
calibrated using the CDMA LMF that is going to be used for the
optimization/calibration. The cable calibration values can also be
entered manually.
. . . continued on next page
3