Installation Instructions

Power, Ground and Battery Cabling for Sites Equipped With Optional
Primary Surge Suppressor
– continued
DEC 2000
5-15
SCt300 BTS Hardware Installation, ATP and FRU Procedures
PRELIMINARY
Table 5-6: Procedure to Install Earth Ground Cable on a BTS
Equipped with Optional Primary Surge Suppressor
Step Action
1 Route cable A (ground cable) from the ground lug on the
mounting bracket to the Primary Surge Suppressor.
2 Connect cable A to the GND connector 1–4 on the Primary
Surge Suppressor.
Table 5-7: Procedure to Install AC Input Cable(s) on a BTS Equipped
with Optional Primary Surge Suppressor
Step Action
1 Connect the customer–supplied AC input cable (cable T) to
the customer defined AC power source. Refer to Table 5-3 for
wiring information.
2 Verify all connections of cable T with an ohmmeter prior to
routing the cable.
3 Route cable T via 1–in. conduit from the customer defined
AC power source to the breaker terminals inside the Primary
Surge Suppressor. Refer to Figure 5-12.
4 Route the AC Input Power Cable (cable S – Motorola part
number 3087854C02) from the Carrier 1–4 AC Output
connector on the Primary Surge Suppressor to the unit
location(s).
5