Installation Instructions
Powering on Unit and Mounting the Solar Cover
PRELIMINARY
SCt300 BTS Hardware Installation, ATP and FRU Procedures
DEC 2000
6-52
Objective
The objective of this procedure is to power on the unit and mount the
solar cover on the chassis.
You May Want to Wait
Do not mount the front solar cover on the unit if you wish to perform the
Acceptance Test Procedures (ATP). Otherwise, mount the front solar
cover until you perform the ATP.
Tools Required
The following tamper–resistant keys are required to do this procedure.
S Key for tamper–resistant stud (provided) for the solar cover.
S Key for tamper–resistant locks (provided) for the Primary Surge
Suppressor.
Procedure to Power On Unit
and Mount Solar Cover
Refer to the procedure in Table 6-45 to power on the unit and mount the
solar cover.
Table 6-45: Procedure to Power on the Unit and Mount the Solar
Cover
Step Action
1
n WARNING
Make sure the unit is properly grounded and that all
connections are connected before powering on unit.
If l i AC 2 If l i AC
If not applying AC power, go to step 2. If applying AC
power, push down on the AC power breaker until it clicks and
remains down. The white collar on the breaker is not visible
when the breaker is closed.
2 If not applying DC power or providing for battery backup, go
to step 3. If applying DC power or have short or long
duration batteries present, push down on the DC power
breaker until it clicks and remains down. The white collar on
the breaker is not visible when the breaker is closed.
3 Position the solar cover so the cooling vents are at the top and
place the solar cover on the unit. Use the key to tighten the
four tamper–resistant studs (two on each side). Refer to
Figure 6-37.
Procedure to Power On Surge
Suppressor, Unit and Mount
Solar Cover
If your BTS is equipped with the Primary Surge Suppressor, refer to the
procedure in Table 6-46 to power on the unit and mount the solar cover.
6