User's Manual

1-6 Configuring, Installing, and Using Carrier Infrastructure
GPS cables
Antenna cables
Ethernet cables
Power cables
Alarm cables
Also, make sure that the fuses are installed properly.
7 Plug in the power cable to the RMBs in the cabinet, make sure the power supply is
working, then turn on each RMB.
BTS installation overview
This section provides a high-level overview of the base station installation process. Other
sections in this guide then explain these installation tasks in detail.
The tasks you perform to deploy base stations are:
1 Mount the base station at the site you selected. For more information, refer to the section
“Mounting and grounding the base station” on page 6-57 in this guide.
2 Connect the antenna to the base station, as described in the section “Connecting the
antenna to the base station” on page 6-59.
3 Mount the GPS device and connect it to the base station. One GPS device can service the
multiple base stations at a cell site. For more information, refer to the section “Connecting
the GPS equipment to a base station” on page 6-59 in this guide.
4 Connect the base station to the transcient voltage suppressor (TVS) module, then connect
the TVS module to your network switch.
The TVS module splits the connection: one connection goes to a switch that connects to
your network, and the other goes to a power supply. For more information, refer to the
section “Connecting to the backbone network” on page 6-60 in this guide.
5 Power the base stations by connecting the TVS module to the power supply. For more
information, refer to the section “Powering base stations” on page 6-61 in this guide.
The TVS module provides lightning protection. The TVS module also splits the
connection: one connection goes to the switch and the other goes to a power supply.
6 Configure cell site switches, the head-end switch, and the ISP switches. For more
information, refer to “Configuring switches” on page 2-12 in this guide.
7 Test the network by working with an ISP to:
Install the ISP’s provisioning server
Test the AP server to Provisioning server connection.
Test that CPEs can access the ISP’s VLAN(s).
Planning the installation
This section describes issues you need to consider before you install the base stations,
including:
Choosing locations for the base station installation
Planning for service provider equipment components
Selecting antennas