Install Instructions
10
Figure 3: Minimum Installation Clearances To Combustible Materials (Inches)
NOTE 1: Listed clearances comply with American National
Standard NFPA 31, Standard for the Installation of Oil
Burning Equipment.
NOTE 2: CL Series boilers can be installed in rooms with
clearances from combustible material as listed above.
Listed clearances cannot be reduced for alcove or closet
installations.
NOTE 3: For reduced clearances to combustible material,
protection must be provided as described in the ANSI/NFPA
31 standard.
C
A
Above
B
Front
Chimney
Connector
D
Rear
E
Sides
6 24 18 6 6
3. For basement installation, provide a solid elevated
base, such as concrete, if oor is not level, or if
water may be encountered on oor around boiler.
4. Provide service clearance of at least 24” clearance
from front jacket panel for servicing and removal
of front tankless heater. If boiler is equipped with
a rear tankless heater, provide at least 24" service
clearance on the right side of the boiler. Boiler
ueways may be cleaned either from the top or from
the right side. Provide at least 24" clearance from
either the right side of the boiler or the top of the
boiler for cleaning ueways.
5. For minimum clearances to combustible materials.
See Figure 3.
NOTICE
Clearance to venting is for single wall vent
pipe. If Type L vent is used, clearance may be
reduced to the minimum required by the vent pipe
manufacturer.
A. INSPECT SHIPMENT CAREFULLY FOR ANY
SIGNS OF DAMAGE.
1. All equipment is carefully manufactured, inspected
and packed. Our responsibility ceases upon delivery
of crated boiler to the carrier in good condition.
2. Any claims for damage or shortage in shipment
must be led immediately against the carrier by
the consignee. No claims for variances from,
or shortage in orders, will be allowed by the
manufacturer unless presented within sixty (60)
days after receipt of goods.
B. LOCATE BOILER NEAR FINAL POSITION
BEFORE REMOVING CRATE. See Figures 1A thru
1C. Using hand truck or pipe rollers under skid, move
boiler into position along side installation site.
1. Locate so that vent pipe connection to chimney will
be short and direct.
2. Boiler is suitable for installation on combustible
oor. Boiler cannot be installed on carpeting.
II: PRE-INSTALLATION