VII: SYSTEM START-UP (continued)
WARNING
Cad Cell Jumper must be removed after this
check.
4. CHECK HIGH LIMIT
a. Adjust system thermostat(s) to highest setting.
b. Allow burner to run until boiler water
temperature exceeds high limit setting. The
burner should shut down and circulators continue
running.
c. Allow the temperature to drop below control
setting. The burner must restart.
d. Boiler installation is not considered complete
until this check has been made.
5. CHECK OPERATING CONTROL on boiler
applications equipped with tankless heater(s). With
burner off, draw hot water until burner starts, then
turn off hot water and check burner shut-down.
K. IF CONTROLS MEET REQUIREMENT outlined
in Paragraph I.
1. Allow boiler to operate for approximately 30
minute, conrm the boiler and system have no leaks.
L. IF CONTROLS DO NOT MEET
REQUIREMENTS outlined in Paragraphs I-1 thru
I-6, replace control and repeat checkout procedures.
M. Boiler is now ready to be put into service.