Do not strip colored insulation from wires, or strip and
twist bare wires prior to inserting in a connector. Insert
insulated colored wires directly into the Scotchloks
connector.
Figure 25 – URCrimping Tool
6. Place the connector (red cap side down) between the
jaws of the UR crimping tool as shown in Figure 25.
Figure 26 – Improper Connections
7. Check to ensure the wires are still fully seated before
crimping the connector. Figure 26 illustrates improper
connections due to wires not fully seated.
Figure 27 – Three Color Wires
Connected
8. Squeeze the connector firmly with the proper crimping
tool until you hear a pop and gel leaks out of the end of
the connector.
9. Repeat steps two through seven for each color wire. See
Figure 27.
10. After all three color wires have been connected, go to
"Testing the Installation" on page1 to ensure proper
connections and the L900 MIU is functioning properly.
20 L900 MIU Pit Installation and Maintenance Guide
Chapter 4: Pit Installation