Follow this procedure to tie the cable and activate the CMIU.
1. Place the CMIU in the pit location:
l In a shallow pit application, you can place the CMIU beside the meter.
l In deep pit applications, use a cable tie to suspend the CMIU from the antenna shaft.
l Do not lodge the CMIU between the meter box and any components inside the box.
Figure 43 – Attaching the CMIU™ to the Antenna Shaft
2. Place the CMIU in such a way that it does not lodge itself when the pit lid is removed.
3. Swipe the CMIU with a magnet:
l Position the magnet against the left side of the CMIU directly in line with the Neptune
logo.
l Move the magnet up and over the top left corner of the CMIU.
Figure 44 – Swiping the CMIU™
Testing the Installation
To test the installation, follow the steps in "Testing the Installation" on page19.
Cellular MIU (CMIU™) Pit and Wall Installation and Maintenance Guide 33
Chapter 5: Pit Installation