Installation Instructions Chapter 2

Pre-Installation Procedures 2-5
Phase 4: Install the DecisioNet Software and Hardware
Infrastructure
The tasks in Phases 4 and 5 are often occurring in parallel but certain
infrastructure tasks must be completed before the SmarTalker tags can
be installed at a site. Phase 4 consists of the following tasks:
Install the CBS infrastructure (Refer to Chapter 4, “Installing the
Hardware Infrastructure.”)
Install Electrical outlets for CBS power supplies
Install the CBS power cable to CBS(s)
Install the communication cable from the EPL controller to the
RS-232/RS-422 Converter
Install the CBS(s) and their antennas in the ceiling
Install communication cables from the converter to first CBS
and from CBS to CBS
Load DecisioNet software (Refer to Chapter 5, “DecisioNet
Software on a Windows NT System,” Chapter 6, “DecisioNet
Software on an NCR UNIX System,” or Chapter 7,“DecisioNet
Software on an SCO UNIX System.”)
Use the EPL Administration application Base Hardware
Configuration screen to define the hardware CBS, power supply
and receive antenna configuration. (Refer to Chapter 8,
“Configuring the DecisioNet System Environment.”)
Test the CBS and RF infrastructure (Refer to Chapter 12, “Testing
the System.”)
Accomplish site certification. For more information on this
procedure, see an NCR representative and reference the
Certification/Re-certification Site Survey Procedure (497-0410343).