Instructions / Assembly
7 
Hard-wire Installation 
"Hard-wire" installation to a power inlet box located remotely from the transfer switch (Figure 
5) requires additional steps to complete the installation.  The wire connections to the wires 
from  power  inlet  box  are  made  in  the  circuit  breaker  compartment  of  the  transfer  switch. 
Access the circuit breaker compartment by removing the two screws located on the sides of 
the  lower  circuit  breaker 
compartment cover. Replace when 
installation is complete. 
From the transfer switch, connect: 
 the  black  wire  lead  to  the 
power inlet X or Y terminal 
 the  white  wire  lead  to  the 
power inlet neutral W terminal 
 the red wire lead to the power 
inlet X or Y terminal 
 the  green  wire  lead  to  the 
power inlet ground G terminal. 
Inlet Installation (For indoor models installed outdoors) 
Suffix A and B models have a power inlet included.  The inlet can be installed on the unit 
by removing the circuit breaker compartment cover (described in the proceeding section) 
and the power inlet filler plate, installing the inlet with the enclosed screws onto the wiring 
compartment  cover,  and  connecting  the  wire  leads  to  the  inlet  as  described  in  the 
instructions included with the inlet. Make sure the unit is installed in a dry location. 
Completing the Installation 
When you have wired all the load circuits in the transfer switch, only the white neutral wire 
and the green ground wire remain. 
1.  Insert  the  white  neutral  wire  into  an  unused  opening  in  the  neutral  bar  in  the  load 
center and tighten the screw (Figure 4). 
2.  Insert the green ground wire into an unused opening in the ground bar, if existing, and 
tighten the screw. If no ground bar exists, insert the green wire into an unused hole in 
the neutral bar and tighten the screw. 
3.  Replace the cover to the load center. 
4  Fill in the chart on the transfer switch to identify your emergency circuits and 
corresponding circuit numbers in the load center. 
5  Return all load center branch circuit and main breakers to the "ON" position. 
6  Move all  circuit  selector  switches  on  the  transfer  switch  to the 
"LINE" position. 
Installation is now complete. 