2.10 Link Up Verification and Initial Commissioning
1. Verify that RF LED is green on the TUs, indicating association (Link UP).
The MultiHaul link can now pass traffic and management between the ports and over
the radio link.
Base-Unit (BU):
1. Verify the BU is pointing towards the sector center (45°) horizontally and to the
farthest terminal unit vertically.
2. Verify the self-locking bands are tightened.
3. Power up the BU and verify Power LED is green.
Terminal Unit (TU):
Up to 8 TUs may be connected to one BU.
1. Point the TU towards the BU. When wall mount is used, verify the BU is located
within the 9 sector’s coverage.
2. Verify the self-locking bands and the Elevation Lock Bolts are locked.
3. Power up the TU and verify Power LED is green. The RF LED should be green,
indicating correct association (Link Up).
Repeat these steps for the next TUs.
Use the Web-based Management or Command Line Interface for radio link configuration