User guide
877-2-MUELLER
E-14
“R” PANEL
Sidelap
1. Sealant tape must be installed between weather infiltration point and fastener.
2. Install Lap Tek fasteners at 20” on center.
3. When possible, install panels such that sidelaps are nested away from prevailing winds.
Endlap
1. Double bead sealant tape must be installed between weather infiltration point and fastener.
2. Install self-drilling fasteners on each side of major ribs of panel (two fasteners per foot).
Detail A Detail B
Lap Tek Screw
(20" O.C.)
Sealant Tape
Sealant Tape
Sealant Tape
Self Drill
(6 each
per panel)
12"
R Panel
Endlap Attachment
(See Detail A)
Sidelap Attachment
(See Detail B)
R Panel
Intermediate Purlin
Attachment
(3 Fasteners Per Panel)
High Side Attachment
(6 Fasteners Per Panel)
Eave Attachment
(6 Fasteners Per Panel)
Slope