ERECTING THE REMAINING FRAMES & EAVE STRUTS
The remaining frames are erected in like manner, initially with only a few purlins being installed in
each bay working from one end of the building to the other. To lend overall rigidity to the structure,
install flange braces to the purlins at specified locations. All purlin, girt and eave strut connection
bolts are left loose so the entire skeleton framework can be plumbed without undue difficulty. The
remaining purlins can be positioned on the rafter in each bay to facilitate the completion of the roof
framing.
NOTE: Take precautions to secure structure during assembly. Temporary
bracing may be required to stabilize the structure during erection.
Never leave the structure unbraced.