Owner manual

DescriptionItem
Nitrogen Bottle14
Nitrogen Bottle Valve15
Regulator Output Pressure Valve16
Regulator Shut-Off Valve17
Nitrogen Bottle Pressure Gage18
Regulator Output Pressure Gage19
Nitrogen Supply Hose20
Extension Hose21
Close22
Bleed Valve23
Open24
Input Check Valve25
High Pressure Gage 0–21 MPa (0–3000 psi)26
Decrease the Pressure
1. Slowly open the bleed valve on the charging kit until gas begins to escape. When the pressure reading
on the appropriate pressure gage drops to the level required, close the bleed valve.
2. Close the locknut. Open the bleed valve on the accumulator charging kit and remove the chuck valve from
the accumulator.
3. Install the valve stem cap and protective cover.
Increase the Accumulator Precharge Pressure
1. Close the locknut on the accumulator.
2. Open the bleed valve two turns.
46 Series 505G2 SilentFlo™ Hydraulic Power Unit Product Information
Installation