Facility Readiness Checklist
Physical space is
ready
Make sure that:
The facility width, length, and ceiling height are adequate to accommodate
the system (Refer to Space Requirements and System Specifications).
The foundation is prepared correctly (refer to Foundation Requirements).
The doors and corridors are large enough to accommodate the system.
Utilities are in place Make sure that:
Qualified electrical power is available (refer to Electrical Power
Requirements and System Specifications).
Qualified hydraulic oil is available (refer to A1.3 of the Installation and
Commissioning Plan).
Arrangements have been made to have trades personnel (electrician,
plumber, and so on.) available to make final connections.
The equipment has
been uncrated and
moved into its final
position
The load frame has been uncrated and anchored to the foundation and
leveled according to Lifting and Moving Instructions.
The Integrated Operations Platform has been uncrated and moved to its final
position and leveled according to Lifting and Moving Instructions.
The accessories (fixtures, steps, safety enclosure, and so on.) are stored
correctly.
Access to facility
network is available
Make sure the computer network connections are available and IT resources
are available to assign IP addresses and ensure the Internet and Intranet are
accessible.
Customer-supplied
parts are available
Make sure all customer-supplied parts and accessories are available and
ready to connect or install. This can include specimen installation fixtures,
environmental equipment, test area guards, and so on.
Specimens are
prepared
Make sure you have all the needed specimens ready for system tests and
training.
Staff available for
training
Make sure personnel who will manage, operate, and service the equipment
are available during installation for training (refer to A1.5 of Installation and
Commissioning Plan).