Installation and Commissioning Plan For CriterionTM Series 60 Customer Name: MTS Project Number: Contract Number: Installation: Date: Customer: Date: be certain.
Installation and Commissioning Plan This Installation and Commissioning Plan is a part of our system service, and is included in the price of the system. The tasks outlined in sections A and B are expected to be completed in two days. The customer is responsible for completing tasks A1.1 through A1.5 before the MTS FSE or MTS Authorized Service Representative (referred to as FSE in rest of this document) arrives on site.
Installation and Commissioning Plan basic test methods. TW4 basic test method templates consist of various tensile, compression, flex and/or peel methods. The descriptions listed below define a list of features that can be modified to create a unique test method for your application (refer to section C3.
Installation and Commissioning Plan • Visitor information. Please provide any visitor restrictions such as security clearance, safety requirements or working hours. The FSE requires at least eight full working hours each day with an additional hour for lunch.
Installation and Commissioning Plan Important 4 • Please expect at least eight full hours of training time. The objectives for the eight hours of training time are listed under A4.0 and B2.0 of this document. The training sessions have been divided into two four-hour sessions to minimize the impact on your daily business activities and to improve the material retention level for the trainees.
Installation and Commissioning Plan A2.0 INSTALLATION PROCEDURE The system will be installed by an FSE. Depending on the system configuration, the following activities will be performed: Item Description Performed On Site A2.1 Verify that all components purchased are present according to the purchase contract and packing list. A2.2 Remove packaging on the load unit (for example mounting clamps and oilpaper). A2.3 Install the cover boards A2.
Installation and Commissioning Plan A3.0 SYSTEM CONFIGURATION AND FUNCTIONAL CHECKS All required activities are to be completed prior to the start of any training activity. The system will also be checked to ensure that all components are operating as intended. Depending on the system configuration, the following activities will be performed. Item Description Performed On Site A3.1 A3.2 6 Load unit functionality checks: - Verify communication and power up operation via handset.
Installation and Commissioning Plan Item Description Performed On Site A3.3 Additional Purchased Options: - Calibrations: See section C1.0 if purchased. System performance demonstrations: See section C2.0 if purchased. Custom test method creation: See section C3.0 if purchased. On-site computer integration: See section C3.0 if purchased. On-site computer integration does not include peripheral or network integration.
Installation and Commissioning Plan INTRODUCTION This Introduction provides a brief overview of the supplied equipment. It is not intended as a substitute for formal training. MTS strongly recommends formal classroom training at the MTS facility in hardware and software operation and maintenance. A4.0 Item System Introduction Description Performed On Site A4.1 A4.2 8 System components: System Start-up and shut down.
Installation and Commissioning Plan FINAL CONFIGURATION & TRAINING B1.0 Final Functional Checks & Configuration Item Description Performed On Site B1.1 Create backup of all critical files. B1.2 Create up to three basic methods according to userdefined specifications. Basic methods are created from a standard compression, tensile, or peel method template. Refer to section A1.5 for definitions of method modifications. B1.
Installation and Commissioning Plan INTRODUCTION This Introduction provides a brief overview of the supplied equipment. It is not intended as a substitute for formal training. MTS strongly recommends formal classroom training at the MTS facility in hardware and software operation and maintenance. Note: The customer shall supply specimens to be used during the system introduction.
Installation and Commissioning Plan PURCHASED OPTIONS: (Extends normal installation plan based on the number of options purchased) C1.0 ON-SITE CALIBRATIONS (purchased option) Item Description Performed On Site C1.1 Perform on-site system calibration of Load, Displacement, Speed, Extensometers or other accessories and/or transducers. C2.
Installation and Commissioning Plan C3.0 CUSTOM METHOD DEVELOPMENT (purchased option) Item Description Performed On Site C3.1 Develop method. C3.2 Run and verify proper test operation. C3.3 Demonstrate test method execution. C3.
Installation and Commissioning Plan C5.0 ADDITIONAL TRAINING AND SERVICES Information regarding the following is available from your MTS local Sales or Service Engineer, or is available from one of MTS' factory locations: - MTS Service Products. - Formal MTS classroom training. - Formal MTS on site training.