Installation and Commissioning Plan User guide

Installation and Commissioning Plan
MTS Criterion
TM
Series 40
7
A2.0 INSTALLATION PROCEDURE
The system will be installed by an FSE. Depending on the system configuration,
the following activities will be performed:
Item Description
Performed
On Site
A2.1 Verify that all components purchased are present
according to the purchase contract and packing list.
A2.2 Attach all required cables between the controller and
load unit.
- Transducers
- Computer
A2.3 Install purchased grips and fixtures as required
(including any auxiliary power supplies for grips).
A2.4 Install purchased environmental simulation products.
(For example, any furnaces, chambers, and baths.)