Installation and Commissioning Plan User guide

Installation and Commissioning Plan
MTS Criterion
TM
Series 40
13
PURCHASED OPTIONS: (Extends normal installation plan based
on the number of options purchased)
C1.0 ON-SITE CALIBRATIONS (purchased option)
Item Description
Performed
On Site
C1.1 Perform on-site system calibrations of load,
displacement, speed, extensometers or other accessories
or transducers.
C2.0 SYSTEM PERFORMANCE DEMONSTRATION (purchased option)
If you purchased an option to have MTS perform demonstrations on the installed
system that are in addition to the installation tasks described in paragraphs A2.0
and A3.0, see note below. For installation, demonstration, and training, the
customer will provide suitable specimens and other materials (for example, CO
2
,
liquid N
2
, temperature scanner, and so forth.) for the type of grips and system
purchased.
Item Description
Performed
On Site
C2.1 Demonstrate system performance of purchased option(s).
These demonstrations can include:
- Verification of published or quoted MTS
performance specifications (see note below).
- Verification of customer performance, accuracy, or
endurance specifications (see note below).
- Performance of particular materials tests (see note
below).
Note: The request for quotation, including specifications or performance to be
demonstrated and clearly defined pass-fail criteria, as well as the MTS
proposal, are attached for reference.