101: With the 6" Sch 40 or Sch 80 steel pipe installed in the ground, place the liing insert
into the top of the pipe unl it sits ush.
102: Place the liing bracket into the liing insert with the eye facing south.
103: Hang a 1 ton or greater chain fall hoist from the liing eye.
104: Hang the U-Bracket Assembly on the Chain Hoist.
105
106
105: While holding the U-Bracket around the pole, insert 3 of the 3/4" x 9” bolts through the holes in the
back of the U-bracket and through the holes on the Back Plate with 3/4” at washers on both sides and
3/4” nuts.
106: Insert the 3/4” x 3” Set Bolts in Back Plate, but do not ghten if leaving chain fall hoist connected.
Note: If installing mulple mounts with a single hoist, bolt the pole cap on the pole at the desired working
height. Tighten 3/4” bolts and 3/4” set screws to 200 -lb. Assemble rack, rails and modules. Then, move
liing assembly and hoist to pole when ready to li. Aach to pole cap and loosen bolts. Connue with
raising the array for wiring or compleng the installaon.