Manual

7
120
121: Insert the 5/8" x 7” bolt over
the top of the pole with the 5/8”
at washers and 5/8” nut.
Securely ghten the 4 tension
bolts in the back of the pole cap to
200 -lb.
122: Remove the chain hoist and
liing bracket and place the 1 3/8”
diameter round cap in place.
122
121
Using an angle nder, adjust
array to proper lt.
Installaon is complete.
119
119: If you are installing modules at ground level, leave a 5” gap to allow for the 4” pipe to protrude
through the array. If you are installing at the top of the pole, you do not need to provide this gap.
120: Once module installaon is complete, raise and or lt the array to facilitate module wiring and
wire management as needed. When wiring is completed, raise the array to the top of the pole.
118: Install Solar Modules as per Mounng Rail and module manufacturer instrucons using top clamps.
See last page of manual for Iron Ridge Rail and Clamp instrucons.