Specifications

EQUIPMENT LIST, PROPOSAL, AND STATEMENT OF WORK
Acceptance Test Plan
R4-11-4G System Planning Process 2-19
2.8.2 Acceptance Test Plan
The project manager, systems engineering, and systems integrator together
create the acceptance test plan (ATP). The ATP can have variations in the test
procedures, depending on the customer’s preferences. The ATP should
include the following:
Cover letter
Executive overview
Detailed list of responsibilities
Motorola responsibilities
Customer responsibilities
Other
System description in detail
Expected system performance in detail
Link verification test with field testing
Procedures for testing in detailed steps
Coverage test of the customer’s area
Guarantee coverage of fixed sites and mobiles
Detailed maps, grids, and test points
Testing at our site or customer’s
References, if required
Literature from LDC (sales brochures)
Capacity testing, confirming mph network capacity
When the ATP is completed, it is given to the contracts department as part of
the SOW.
2.8.3 Assembling the Proposal
Sales and systems engineering working together create the proposal
documents for presentation to the customer. Proposal text and support
information are available in various Private DataTAC documents shown in
the References section of this document.
Part of the proposal should include training for Motorola’s portion of the
solution. The customer needs to be trained on the process, as modified, using
the equipment and software. This training should occur before and after
equipment installation.